       No.
      
       
     | 
    
       Questions
      
       
     | 
    
       Example
      
       
     | 
    
       Some points to
      consider 
      
       
     | 
     | 
  
  
    | 
       1
      
       
     | 
    
       Please insert the
      name of the organisation
      
       
     | 
    
       IFRC
      
       
     | 
    
       The name of the
      organisation implementing the programme/project
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       2
      
       
     | 
    
       Please insert the
      name of the project or programme
      
       
     | 
    
       Community-Based
      Disaster Preparedness Program (CBDP): Training-Action-Reflection Approach
      to Capacity Building
      
       
     | 
     | 
  
  
    | 
       2
      
       
     | 
    
          | 
  
  
    | 
       3
      
       
     | 
    
       What is the
      starting and finishing project/programme dates.
      
       
     | 
    
       1995-2000 (5yrs)
      
       
     | 
    
       Please also include
      initiatives earlier than year 2000 that are still underway.
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       4
      
       
     | 
    
       Where is the
      programme/project being implemented?
      
       
     | 
    
       Bangladesh
      (National)
      
       
     | 
    
       Is it a national
      level project? Which provinces, states, districts, municipalities is the
      project implemented 
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       5
      
       
     | 
    
       What type of
      support did your organisation provide during the implementation of the
      project/programme
      
       
     | 
    
       Technical (Capacity
      Building)
      
       
     | 
    
       Support can be
      categorised as technical and financial
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       6
      
       
     | 
    
       Which
      organization(s) were involved in funding the project/programme?
      
       
     | 
    
       German Red Cross (GRC),
      Swiss Red Cross (SRC)
      
       
     | 
    
       Source(s) of
      funding the programme/project
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       7
      
       
     | 
    
       What was the total
      funding amount (in US$)?
      
       
     | 
    
       NAV
      
       
     | 
    
       Please provide the
      amount in local currency and equivalent to US$
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       8
      
       
     | 
    
       Which local partner
      organisation(s) was responsible for implementing the project/programme?
      
       
     | 
    
       Bangladesh Red
      Crescent Society (BDRCS)
      
       
     | 
    
       This would be the
      relevant national and local level authorities and organizations.
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       9
      
       
     | 
    
       Please list down
      briefly the secondary objectives of the programme/project.
      
       
     | 
    
       To build capacity
      of BDRCS's staff to implement CBDP by shifting their approach from a
      relief orientation to a community based participatory approach to risk and
      vulnerability reduction.
      
       
     | 
    
       Focus on more
      specific objectives, as compared to development objectives
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       10
      
       
     | 
    
       What were the key
      activities carried out during the implementation phase?
      
       
     | 
    
       Conducting
      participatory assessment (using PRA) to understand the multi-dimensional
      character and local conception on the dimensions of disaster,
      vulnerability and risk management; Approach setting workshop for CBDP and
      other stakeholders; Capacity needs assessment for enabling BDRCS staff to
      implement the approach; Piloting the approach
      
       
     | 
    
       Please focus on the
      type of activities.
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       11
      
       
     | 
    
       If the project/programme
      is in progress, please mention the expected targeted outputs.
      
       
     | 
    
       Not Applicable (NA)
      
       
     | 
    
       Please try to focus
      on the outputs as compared to the outcomes. Outputs are short term in
      nature and tangible.
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       12
      
       
     | 
    
       If the project/programme
      is completed, please mention the achieved outputs
      
       
     | 
    
       Local communities'
      participation and resource mobilization enhanced; formation of many
      Community Disaster Preparedness Committees and introduction of
      participatory planning monitoring evaluation system; identification of
      appropriate local technologies.
      
       
     | 
     | 
  
  
     | 
  
  
    | 
       13
      
       
     | 
    
       What approach was
      undertaken during the implementation?
      
       
     | 
    
       Consultative
      approach was undertaken with the team consisting of BDRC Headquarters,
      Field Officers and Unit Representatives.
      
       
     | 
    
       What was the
      process of implementing the initiative? 
      
       
     | 
     | 
  
  
     | 
  
  
     | 
  
  
    | 
       14
      
       
     | 
    
       How would you
      define the category of the initiatives?
      
       
     | 
    
       Preparedness
      
       
     | 
    
       The categories
      would be preparedness, prevention, knowledge management, networking and
      alliance building. 
      
       
     | 
     | 
  
  
    | 
       15
      
       
     | 
    
       Can you summarize
      in brief the performance of the project/programme?
      
       
     | 
    
       NAV
      
       
     | 
    
       Very satisfactory,
      satisfactory, fair, poor. 
      
       
     | 
     |